Stoke Sports and Community Facility

stoke community centre front elevation

Contractor: Watts and Hughes Construction
Project Manager: Onus Construction Management
Budget: $6.15 million
Status: Under construction
Time frame: 3 years

Progress

Resource Consent Hearing was held on 23 February 2016.

The new facility will is progressing well, with physical works having started in December 2016. All foundation work has been built up and drainage work and floor slabs poured.

For more information click here

 

Background

Over the next thirty years Stoke is expected to be home to three quarters of Nelson’s population growth and half its new housing. Council has recognised the need for appropriate facilities and services to support this growth forecast. After extensive consultation with the community, Council has approved plans for a new sports and community facility at Greenmeadows reserve, with an additional space that could be used as a cafe in the future.

Further projects which have been included in the Plan include discussions with the community on the future of Stoke Hall and how it can best fit with the new Greenmeadows facility; consultation, planning and physical works for a youth park; an extension to the Library and further improvements to parking and transport issues.

Click here for more information and concept plans